Time line in Vue Gantt component
16 Mar 202324 minutes to read
In the Gantt component, timeline is used to represent the project duration as individual cells with defined unit and formats.
Timeline view modes
Gantt contains the following in-built timeline view modes:
- Hour – Minute
- Day – Hour
- Week – Day
- Month – Week
- Year – Month
Timescale mode in the Gantt component can be defined using the timelineViewMode
property, and you can define a timescale mode for the top tier and bottom tier using the topTier.unit
and bottomTier.unit
properties.
Week timeline mode
In the Week
timeline mode, the upper part of the schedule header displays the weeks, whereas the bottom half of the header displays the days. Refer to the following code example.
<template>
<div>
<ejs-gantt id="GanttContainer" :dataSource="data" :taskFields = "taskFields" :height = "height" :timelineSettings="timelineSettings"></ejs-gantt>
</div>
</template>
<script>
import Vue from "vue";
import { GanttPlugin } from "@syncfusion/ej2-vue-gantt";
Vue.use(GanttPlugin);
export default {
data: function() {
return{
data: [
{
TaskID: 1,
TaskName: 'Project Initiation',
StartDate: new Date('04/02/2019'),
EndDate: new Date('04/21/2019'),
subtasks: [
{ TaskID: 2, TaskName: 'Identify Site location', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50 },
{ TaskID: 3, TaskName: 'Perform Soil test', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50 },
{ TaskID: 4, TaskName: 'Soil test approval', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50 },
]
},
{
TaskID: 5,
TaskName: 'Project Estimation',
StartDate: new Date('04/02/2019'),
EndDate: new Date('04/21/2019'),
subtasks: [
{ TaskID: 6, TaskName: 'Develop floor plan for estimation', StartDate: new Date('04/04/2019'), Duration: 4, Progress: 50 },
{ TaskID: 7, TaskName: 'List materials', StartDate: new Date('04/04/2019'), Duration: 4, Progress: 50 },
{ TaskID: 8, TaskName: 'Estimation approval', StartDate: new Date('04/04/2019'), Duration: 4, Progress: 50 }
]
},
],
height: '450px',
taskFields: {
id: 'TaskID',
name: 'TaskName',
startDate: 'StartDate',
endDate: 'EndDate',
duration: 'Duration',
progress: 'Progress',
dependency: 'Predecessor',
child: 'subtasks'
},
timelineSettings: {
timelineViewMode:'Week',
},
};
},
};
</script>
Month timeline mode
In the Month
timeline mode, the upper part of the schedule header displays the months, whereas the bottom header of the schedule displays its corresponding weeks. Refer to the following code example.
<template>
<div>
<ejs-gantt id="GanttContainer" :dataSource="data" :taskFields = "taskFields" :height = "height" :timelineSettings="timelineSettings"></ejs-gantt>
</div>
</template>
<script>
import Vue from "vue";
import { GanttPlugin } from "@syncfusion/ej2-vue-gantt";
Vue.use(GanttPlugin);
export default {
data: function() {
return{
data: [
{
TaskID: 1,
TaskName: 'Project Initiation',
StartDate: new Date('04/02/2019'),
EndDate: new Date('04/21/2019'),
subtasks: [
{ TaskID: 2, TaskName: 'Identify Site location', StartDate: new Date('04/02/2019'), Duration: 14, Progress: 50 },
{ TaskID: 3, TaskName: 'Perform Soil test', StartDate: new Date('04/02/2019'), Duration: 14, Progress: 50 },
{ TaskID: 4, TaskName: 'Soil test approval', StartDate: new Date('04/02/2019'), Duration: 14, Progress: 50 },
]
},
{
TaskID: 5,
TaskName: 'Project Estimation',
StartDate: new Date('04/02/2019'),
EndDate: new Date('04/21/2019'),
subtasks: [
{ TaskID: 6, TaskName: 'Develop floor plan for estimation', StartDate: new Date('04/04/2019'), Duration: 14, Progress: 50 },
{ TaskID: 7, TaskName: 'List materials', StartDate: new Date('04/04/2019'), Duration: 14, Progress: 50 },
{ TaskID: 8, TaskName: 'Estimation approval', StartDate: new Date('04/04/2019'), Duration: 14, Progress: 50 }
]
},
],
height: '450px',
taskFields: {
id: 'TaskID',
name: 'TaskName',
startDate: 'StartDate',
endDate: 'EndDate',
duration: 'Duration',
progress: 'Progress',
dependency: 'Predecessor',
child: 'subtasks'
},
timelineSettings: {
timelineViewMode:'Month',
timelineUnitSize:150,
},
};
},
};
</script>
Year timeline mode
In the Year
timeline mode, the upper schedule header displays the years whereas, the bottom header displays its corresponding months. Refer to the following code example.
<template>
<div>
<ejs-gantt id="GanttContainer" :dataSource="data" :taskFields = "taskFields" :height = "height" :timelineSettings="timelineSettings"></ejs-gantt>
</div>
</template>
<script>
import Vue from "vue";
import { GanttPlugin } from "@syncfusion/ej2-vue-gantt";
import { editingData } from './data-source.js';
Vue.use(GanttPlugin);
export default {
data: function() {
return{
data: [
{
TaskID: 1,
TaskName: 'Project Initiation',
StartDate: new Date('04/02/2019'),
EndDate: new Date('04/21/2019'),
subtasks: [
{ TaskID: 2, TaskName: 'Identify Site location', StartDate: new Date('04/02/2019'), Duration: 54, Progress: 50 },
{ TaskID: 3, TaskName: 'Perform Soil test', StartDate: new Date('04/02/2019'), Duration: 54, Progress: 50 },
{ TaskID: 4, TaskName: 'Soil test approval', StartDate: new Date('04/02/2019'), Duration: 54, Progress: 50 },
]
},
{
TaskID: 5,
TaskName: 'Project Estimation',
StartDate: new Date('04/02/2019'),
EndDate: new Date('04/21/2019'),
subtasks: [
{ TaskID: 6, TaskName: 'Develop floor plan for estimation', StartDate: new Date('04/04/2019'), Duration: 54, Progress: 50 },
{ TaskID: 7, TaskName: 'List materials', StartDate: new Date('04/04/2019'), Duration: 54, Progress: 50 },
{ TaskID: 8, TaskName: 'Estimation approval', StartDate: new Date('04/04/2019'), Duration: 54, Progress: 50 }
]
},
],
height: '450px',
taskFields: {
id: 'TaskID',
name: 'TaskName',
startDate: 'StartDate',
endDate: 'EndDate',
duration: 'Duration',
progress: 'Progress',
dependency: 'Predecessor',
child: 'subtasks'
},
timelineSettings: {
timelineViewMode:'Year',
timelineUnitSize:70
},
};
},
};
</script>
Day timeline mode
In the Day
timeline mode, the upper part of the header displays the days whereas, the bottom schedule header displays its corresponding hours. Refer to the following code example.
<template>
<div>
<ejs-gantt id="GanttContainer" :dataSource="data" :taskFields = "taskFields" :height = "height" :timelineSettings="timelineSettings"></ejs-gantt>
</div>
</template>
<script>
import Vue from "vue";
import { GanttPlugin } from "@syncfusion/ej2-vue-gantt";
Vue.use(GanttPlugin);
export default {
data: function() {
return{
data: [
{
TaskID: 1,
TaskName: 'Project Initiation',
StartDate: new Date('04/02/2019'),
EndDate: new Date('04/21/2019'),
isParent:true,
subtasks: [
{ TaskID: 2, TaskName: 'Identify Site location', StartDate: new Date('04/02/2019'), Duration: 2, Progress: 50,isParent:false },
{ TaskID: 3, TaskName: 'Perform Soil test', StartDate: new Date('04/02/2019'), Duration: 2, Progress: 50, resources: [2, 3, 5],isParent:false },
{ TaskID: 4, TaskName: 'Soil test approval', StartDate: new Date('04/02/2019'), Duration: 2,Predecessor:"2FS", Progress: 50,isParent:false },
]
},
],
height: '450px',
taskFields: {
id: 'TaskID',
name: 'TaskName',
startDate: 'StartDate',
endDate: 'EndDate',
duration: 'Duration',
progress: 'Progress',
dependency: 'Predecessor',
child: 'subtasks'
},
timelineSettings: {
timelineViewMode:'Day',
},
};
},
};
</script>
Hour timeline mode
An Hour
timeline mode tracks the tasks in minutes scale. In this mode, the upper schedule header displays hour scale and the lower schedule header displays its corresponding minutes.
<template>
<div>
<ejs-gantt id="GanttContainer" :dataSource="data" :taskFields = "taskFields" :height = "height" :timelineSettings="timelineSettings"></ejs-gantt>
</div>
</template>
<script>
import Vue from "vue";
import { GanttPlugin } from "@syncfusion/ej2-vue-gantt";
Vue.use(GanttPlugin);
export default {
data: function() {
return{
data: [
{
TaskID: 1,
TaskName: 'Project Initiation',
StartDate: new Date('04/02/2019'),
EndDate: new Date('04/21/2019'),
isParent:true,
subtasks: [
{ TaskID: 2, TaskName: 'Identify Site location', StartDate: new Date('04/02/2019'), Duration: 2, Progress: 50,isParent:false },
{ TaskID: 3, TaskName: 'Perform Soil test', StartDate: new Date('04/02/2019'), Duration: 2, Progress: 50, resources: [2, 3, 5],isParent:false },
{ TaskID: 4, TaskName: 'Soil test approval', StartDate: new Date('04/02/2019'), Duration: 2,Predecessor:"2FS", Progress: 50,isParent:false },
]
},
],
height: '450px',
taskFields: {
id: 'TaskID',
name: 'TaskName',
startDate: 'StartDate',
endDate: 'EndDate',
duration: 'Duration',
progress: 'Progress',
dependency: 'Predecessor',
child: 'subtasks'
},
timelineSettings: {
timelineViewMode:'Hour',
},
};
},
};
</script>
Week start day customization
In the Gantt component, you can customize the week start day using the weekStartDay
property. By default, the weekStartDay
is set to 0
, which specifies the Sunday as a start day of the week. But, you can customize the week start day by using the following code example.
<template>
<div>
<ejs-gantt id="GanttContainer" :dataSource="data" :taskFields = "taskFields" :height = "height" :timelineSettings="timelineSettings"></ejs-gantt>
</div>
</template>
<script>
import Vue from "vue";
import { GanttPlugin } from "@syncfusion/ej2-vue-gantt";
Vue.use(GanttPlugin);
export default {
data: function() {
return{
data: [
{
TaskID: 1,
TaskName: 'Project Initiation',
StartDate: new Date('04/02/2019'),
EndDate: new Date('04/21/2019'),
subtasks: [
{ TaskID: 2, TaskName: 'Identify Site location', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50 },
{ TaskID: 3, TaskName: 'Perform Soil test', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50 },
{ TaskID: 4, TaskName: 'Soil test approval', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50 },
]
},
{
TaskID: 5,
TaskName: 'Project Estimation',
StartDate: new Date('04/02/2019'),
EndDate: new Date('04/21/2019'),
subtasks: [
{ TaskID: 6, TaskName: 'Develop floor plan for estimation', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50 },
{ TaskID: 7, TaskName: 'List materials', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50 },
{ TaskID: 8, TaskName: 'Estimation approval', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50 }
]
},
],
height: '450px',
taskFields: {
id: 'TaskID',
name: 'TaskName',
startDate: 'StartDate',
endDate: 'EndDate',
duration: 'Duration',
progress: 'Progress',
dependency: 'Predecessor',
child: 'subtasks'
},
timelineSettings: {
timelineViewMode:'Week',
weekStartDay:3
},
};
},
};
</script>
Customize automatic timescale update action
In the Gantt component, the schedule timeline will be automatically updated when the tasks date values are updated beyond the project start date and end date ranges. This can be enabled or disabled using the updateTimescaleView
property.
<template>
<div>
<ejs-gantt id="GanttContainer" :dataSource="data" :taskFields = "taskFields" :height = "height" :timelineSettings="timelineSettings" :editSettings="editSettings"></ejs-gantt>
</div>
</template>
<script>
import Vue from "vue";
import { GanttPlugin,Edit } from "@syncfusion/ej2-vue-gantt";
Vue.use(GanttPlugin);
export default {
data: function() {
return{
data: [
{
TaskID: 1,
TaskName: 'Project Initiation',
StartDate: new Date('04/02/2019'),
EndDate: new Date('04/21/2019'),
subtasks: [
{ TaskID: 2, TaskName: 'Identify Site location', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50 },
{ TaskID: 3, TaskName: 'Perform Soil test', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50 },
{ TaskID: 4, TaskName: 'Soil test approval', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50 },
]
},
{
TaskID: 5,
TaskName: 'Project Estimation',
StartDate: new Date('04/02/2019'),
EndDate: new Date('04/21/2019'),
subtasks: [
{ TaskID: 6, TaskName: 'Develop floor plan for estimation', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50 },
{ TaskID: 7, TaskName: 'List materials', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50 },
{ TaskID: 8, TaskName: 'Estimation approval', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50 }
]
},
],
height: '450px',
taskFields: {
id: 'TaskID',
name: 'TaskName',
startDate: 'StartDate',
endDate: 'EndDate',
duration: 'Duration',
progress: 'Progress',
dependency: 'Predecessor',
child: 'subtasks'
},
timelineSettings: {
updateTimescaleView:false
},
editSettings:{
allowEditing:true,
allowTaskbarEditing:true
}
};
},
provide: {
gantt: [ Edit ]
},
};
</script>